The process and duration of using a AC Resonant Test System to withstand voltage on cables

18 Apr 2024
  In the power system,the proper functioning of cables is of great significance as they carry electricity.Any malfunction during the power transmission process can lead to power outages in the supply area,significantly impacting people's lives.Therefore,it is essential to conduct withstand voltage testing on cables.Typically,for high-voltage cables,we use AC Resonant Test System for the testing.So,what is the process and duration of conducting cable withstand voltage testing using AC Resonant Test System?Let's find out.

  During the cable withstand voltage test using AC Resonant Test System,the complete process and duration may vary depending on specific circumstances.Here are the approximate steps and time required:

  1.Preparation:This includes checking and ensuring the power supply,reactors,grounding wires,and other equipment of the series resonance test apparatus are in order,and correctly connecting the test circuit as required.This step takes about 10 minutes.

  2.Setting test parameters:Based on the capacitance of the test specimen,test frequency,test voltage,test duration,etc.,set the parameters of the AC Resonant Test System.This step takes about 10 minutes.

  3.Conducting the test:Connect the test specimen to the AC Resonant Test System and start the withstand voltage test.This step takes about 5 minutes.

  4.Observing test results:During the test,closely observe the condition of the test specimen and record the test results.This step takes about 10 minutes.

  5.Test completion:After the test is finished,remove the test specimen from the AC Resonant Test System and turn off the power.This step takes about 5 minutes.

  In summary,conducting cable withstand voltage testing using AC Resonant Test System typically takes between 30 minutes to 1 hour,with the specific duration varying based on the test specimen and requirements.During the test,strict adherence to safety procedures,reliable grounding,and maintaining a safe operating distance are crucial.